1231 Comstock Prime Data Center, San Jose

approved Campus

Operated by Prime Data Centers

The 1231 Comstock Prime Data Center is a four-story, approximately 109,520 square foot data center that the City of San Jose reviewed under a Mitigated Negative Declaration (SCH 2024070671).

Land use jurisdiction: City of San Jose

01

Measurements on record

Size

Building area 109,520 sq ft (design) source

Water and cooling

Water use not yet requested

No figure is on public record for this facility. Absence of a record here is a records gap, not a finding about the facility.

The record that would establish it

Water supply (will-serve). not yet requested permitting path

How to read water figures

The same figure can read as large or small depending on the frame. A county comparison puts it beside documented local withdrawals; a national total would make any single facility look small. Cooling design matters as much as quantity, and water used to generate a facility's electricity is not included here. Full methodology

Cooling type not yet requested

No figure is on public record for this facility. Absence of a record here is a records gap, not a finding about the facility.

The record that would establish it

Water supply (will-serve). not yet requested permitting path

How to read water figures

The same figure can read as large or small depending on the frame. A county comparison puts it beside documented local withdrawals; a national total would make any single facility look small. Cooling design matters as much as quantity, and water used to generate a facility's electricity is not included here. Full methodology

Economics

Permanent jobs 20 jobs (design) source
02

Permitting path

Approvals on record for 1 of 12 path steps.

California runs environmental review with the land-use entitlement: the lead agency for CEQA is usually the land-use authority, so the two milestones move together. Large onsite generation adds a California Energy Commission authorization.

DateStepAuthorityInstrumentStatus
Site control (deed or lease) not yet requested
CEQA review City of San Jose Mitigated Negative Declaration (SCH 2024070671)
Mitigated Negative Declaration (SCH 2024070671) (original)
on record
Entitlement (CUP / site plan) City of San Jose not yet requested
CEC authorization (SPPE / AFC)
applies onsite generation of 50 MW or more
California Energy Commission not yet requested
Natural gas service
applies where the facility uses natural gas
not yet requested
Grid interconnection not yet requested
Sewer will-serve City of San Jose (sewer service) (municipal limits) not yet requested
Will-serve letter / water supply assessment not yet requested
Building permit City of San Jose not yet requested
Stormwater (construction general permit)
applies where land disturbance is one acre or more
California State Water Resources Control Board not yet requested
Air district permit (generators) Bay Area Air Quality Management District not yet requested
Public agreements and incentives
applies where negotiated with the host jurisdiction
City of San Jose not yet requested
Go-live not yet live

Steps without a record are shown as not yet requested or not on record: absence of a record here is a records gap, not a finding about the facility. An authority shown for an empty step is the body that would issue it. Some authorities are shown before any record exists, from mapped utility service areas or, for sewer service, from municipal limits; these carry a marker naming the basis.

Site control comes first in every path: a proponent must hold a deed, lease, or purchase option on every parcel of the site before it can apply. Parcel and ownership records have not yet been pulled for this facility.

About this path and the law behind each step: the law on record for this jurisdiction

03

Location and sources

San Jose, Santa Clara County, California

Every record links to its source: public records, press reporting, and openly licensed datasets including Epoch AI, Wikidata, and US EPA. Full sourcing and per-source licensing: methodology · sources.