SVY03A Data Center Campus
approved CampusOperated by STACK Infrastructure
The SVY03A Data Center Campus in Hayward, developed by STACK Infrastructure on 11.3 acres, was reviewed by the California Energy Commission under a Mitigated Negative Declaration (SCH 2025030999) and includes an emergency backup generating facility of up to 67.2 MW.
Land use jurisdiction: City of Hayward
01
Measurements on record
02
Approvals, by aspect
| Aspect | Approving body | Instrument | Status |
|---|---|---|---|
| CEQA review | California Energy Commission | Mitigated Negative Declaration (SCH 2025030999) document |
on record |
| Land use entitlement (CUP / rezoning) | not yet requested | ||
| Building permit | not yet requested | ||
| Air permit (backup generators) | not yet requested | ||
| Water supply (will-serve) | not yet requested | ||
| Wastewater / septic | not yet requested | ||
| Stormwater / retention ponds / dry wells | not yet requested | ||
| Grid interconnection | not yet requested | ||
| Natural gas supply | not yet requested | ||
| Tax abatement / development agreement | not yet requested |
03
Location and sources
Hayward, Alameda County, California
Every record links to its source: openly licensed datasets (Epoch AI, CC BY; Wikidata, CC0; US EPA, public domain) and public permit records. Full sourcing and licensing: methodology · sources.