K2 Data Centres Ballycoolin, Ballycoolin

operational Campus

Operated by K2 Data Centres

A three-building K2 (Keppel) campus at Orion Business Park, Ballycoolin, built on a former transport depot site under Fingal County Council permissions.

Land use jurisdiction: Fingal County Council

01

Measurements on record

No disclosed measurements on record yet.

02

Permitting path

No approvals on record yet for any of the 12 path steps.

Ireland's path runs grid-first: under the CRU's Large Energy Users Connection Policy (CRU/25/236, December 2025, replacing the 2021 data centre connection direction), a new connection offer requires dispatchable generation or storage matched to the facility's import capacity and a commitment to source at least 80 percent of annual demand from new Irish renewable generation within six years of energisation. Planning permission sits with the local authority in the first instance (the 2018 provision routing large data centres directly to the national planning body is not yet commenced), with appeals to An Coimisiun Pleanala, and environmental impact assessment where screening requires it. Uisce Eireann water and wastewater connections, building control certificates, and an EPA industrial emissions licence for standby fleets over 50 MW thermal complete the path.

DateStepAuthorityInstrumentStatus
Site control (title or lease) Tailte Éireann not yet requested
Grid connection application EirGrid not yet requested
Connection offer and agreement EirGrid not yet requested
Dispatchable generation or storage matched to import capacity
applies for new connection applications under the 2025 policy
Commission for Regulation of Utilities not yet requested
Renewables matching commitment (80 percent in six years)
applies for new connection applications under the 2025 policy
Commission for Regulation of Utilities not yet requested
Strategic infrastructure pre-application consultation
applies where an associated Seventh Schedule class, such as large scale onsite generation, routes the application to An Coimisiun Pleanala; the data centre specific route is not yet commenced
An Coimisiún Pleanála not yet requested
Environmental impact assessment
applies where screening determines significant effects are likely
Fingal County Council not yet requested
Planning permission Fingal County Council not yet requested
Uisce Eireann wastewater connection Uisce Éireann not yet requested
Uisce Eireann water connection agreement Uisce Éireann not yet requested
Building control (commencement notice; fire safety and disability access certificates) Fingal County Council not yet requested
EPA industrial emissions licence
applies where standby generation crosses licensing thresholds
Environmental Protection Agency not yet requested
Go-live date not on record live

Steps without a record are shown as not yet requested or not on record: absence of a record here is a records gap, not a finding about the facility. An authority shown for an empty step is the body that would issue it. Some authorities are shown before any record exists, from mapped utility service areas or, for sewer service, from municipal limits; these carry a marker naming the basis.

Site control comes first in every path: a proponent must hold a deed, lease, or purchase option on every parcel of the site before it can apply. Parcel and ownership records have not yet been pulled for this facility.

About this path and the law behind each step: the law on record for this jurisdiction

03

Location and sources

Ballycoolin, Fingal County Council, Ireland

Sources: DataCenterDynamics: K2 Data Centres plans two Dublin facilities · K2 Data Centres official site