Data-center law in Ireland
National jurisdiction · as of 2026-10-14
AIDrafted with AI
Drafted with AI from the cited sources under the direction of UnGovr staff. UnGovr holds editorial responsibility for this page. How this site is made
Ireland's data-centre permitting path is grid-first and multi-track. A developer engages the electricity system operators early under the CRU's Large Energy Users Connection Policy (CRU/25/236, December 2025, replacing the 2021 data-centre connection direction), which conditions any new connection offer on dispatchable generation or storage matched to import capacity and on sourcing at least 80 percent of annual demand from new Irish renewable generation within six years of energisation.
Planning permission goes to the local planning authority in the first instance, because the 2018 provision that would route large data centres directly to the national planning body as strategic infrastructure has not been commenced; appeals go to An Coimisiun Pleanala, the renamed An Bord Pleanala. There is no dedicated data-centre EIA class, so environmental impact assessment is triggered through the general screening duty where significant effects are likely.
Standby generation fleets with a combined total rated thermal input of 50 MW or more need an EPA industrial emissions licence, building control runs in parallel with planning, and water and wastewater connections come from Uisce Eireann under a CRU-approved charging policy. Government policy overlays the path without adding consents: the July 2022 Government Statement and the January 2026 Large Energy User Action Plan favour renewable-co-located, grid-efficient projects.
Revenue gives capital allowances for plant and machinery at a rate of 12.5 percent over eight years, and a 100 percent accelerated allowance for listed energy-efficient equipment. Construction work is also subject to the Safety, Health and Welfare at Work (Construction) Regulations 2013, which apply to and in relation to construction work.
Under section 24 of the Air Pollution Act 1987, the occupier of any premises, other than a private dwelling, must use the best practicable means to limit and, if possible, to prevent an emission from the premises.
01
Instruments on record
16 instruments on record, grouped by the family of approval each one governs.
Land use
Who decides whether a data center may occupy a site, and through what approval?
Government Statement on the Role of Data Centres in Ireland's Enterprise Strategy
In force
Government of Ireland policy statement, July 2022
Effective 2022-07-27 · Applies to government
Cross-government principles for assessing data-centre development. The Government prefers developments associated with strong economic activity and employment. It prefers developments that make efficient use of the electricity grid, using available capacity and alleviating constraints. It prefers locations where a renewable generation facility or advanced storage can be co-located with the data centre.
The principles apply subject to the requirements of the applicable planning and grid connection processes. The January 2026 Large Energy User Action Plan states that data-centre developments will continue to adhere to these principles.
Source: Full text of law
Planning and Development Act 2000
In force
No. 30 of 2000, as amended; strategic infrastructure route at sections 37A to 37J
Applies to both
Applications for development specified in the Seventh Schedule go to the Board under section 37E, not to a planning authority. A 2018 amendment would add a facility of more than 10,000 square metres used primarily for the storage, management and dissemination of data to the Seventh Schedule. Section 49 of the Planning and Development (Amendment) Act 2018 has not been commenced. A decision of a planning authority on an application for permission under section 34 may be appealed to the Board. The Board, An Bord Pleanala, now stands renamed An Coimisiun Pleanala.
Source: Full text of law
Planning and Development Act 2024
Enacted, not yet in force
No. 34 of 2024, phased commencement
Applies to both
A consolidation and revision of the planning code. The Act was enacted on 17 October 2024. It commences by order, provision by provision. An Bord Pleanala continued in being and was renamed An Coimisiun Pleanala. That change took effect on 18 June 2025 under Statutory Instrument No. 256 of 2025, when sections 494 to 531 of Part 17 commenced.
The Irish Statute Book's commencement table, updated to 17 September 2026, shows the development consents provisions in sections 82 to 179 as not yet commenced. It also shows the environmental assessment provisions in sections 208 to 241 as not yet commenced. It shows the repeal of the Planning and Development Act 2000 in section 6 as commenced only in part.
Source: Full text of law
Environmental review
What impact review must precede approval, and who leads it?
Planning and Development Regulations 2001 (EIA screening)
In force
S.I. No. 600 of 2001, Schedule 5, with sections 176A to 176C of the 2000 Act
Effective 2002-03-11 · Applies to both
Part 2 of Schedule 5 names no data-centre class, and includes urban development involving an area greater than 2 hectares in a business district, 10 hectares in other parts of a built-up area and 20 hectares elsewhere. A development of a Schedule 5 class that falls below the stated limit may be submitted to the planning authority for screening for environmental impact assessment.
Source: Full text of law
Energy and grid
What authorizations govern grid connection and onsite generation?
Electricity Regulation Act 1999
In force
No. 23 of 1999, as amended
Applies to both
The statutory basis for the Commission for Regulation of Utilities and for licensing of generation and supply; the legal foundation under which the CRU issues its connection-policy decisions.
Source: Full text of law
Large Energy User Action Plan (LEAP)
In force
Department of Enterprise, Tourism and Employment, 13th January 2026
Effective 2026-01-13 · Applies to government
A framework of 17 actions that prepares for a plan-led approach to the co-location of the most energy-intensive large energy user sectors with renewable energy supply within green energy park locations. It names data centres among the energy-intensive sectors it is meant to attract. Data-centre developments will continue to adhere to the principles of the 2022 Government Statement. The CRU's December 2025 connection policy sets the criteria for connecting new data centres to the electricity network.
Source: Full text of law
Large Energy Users Connection Policy (CRU/2025236)
In force
CRU/2025236, decision of 12 December 2025
Effective 2025-12-12 · Applies to private
The operative electricity connection policy for data centres. A data centre with a maximum import capacity of 10 MVA or more must provide dispatchable onsite or proximate generation or storage capacity matched to that capacity, participating in the wholesale electricity market. A data centre at or above the 1 MVA de-minimis level must meet at least 80 percent of its annual electricity demand with additional renewable electricity generated in Ireland.
It has a six-year glide path, from the date its demand site is energised, to reach that level. Applications received before the decision and still being processed continue under the 2021 direction (CRU/21/124).
Source: Full text of law
Direction on data centre grid connection processing (CRU/21/124)
Superseded
CRU/21/124, direction of November 2021
Effective 2021-11-23 · Applies to private
Directed EirGrid and ESB Networks to apply assessment criteria, including grid constraint at the location, onsite generation, and demand flexibility, before making any data-centre connection offer. Superseded by CRU/25/236 for new applications; pre-existing applications continue to be processed under it.
Source: Full text of law
Water and utilities
Who commits water and sewer service, and under what assessment?
Construction
What codes and permits govern the build itself?
Building Control Acts 1990 and 2007
In force
No. 3 of 1990 and No. 21 of 2007; Building Control (Amendment) Regulations 2014 (S.I. No. 9 of 2014)
Applies to both
Each local authority is a building control authority. Subject to limited exemptions, a commencement notice must be submitted in advance of the construction of a new building, the extension of a building or the alteration of a building. A building or works may also require a fire safety certificate, a disability access certificate and a certificate of compliance on completion.
Source: Full text of law
Safety, Health and Welfare at Work (Construction) Regulations 2013 (client and project supervisor duties)
In force
S.I. No. 291 of 2013, Safety, Health and Welfare at Work (Construction) Regulations 2013
Effective 2013-08-01 · Applies to both
The Regulations apply to and in relation to construction work. A client must not appoint a person as project supervisor for the design process for a project unless reasonably satisfied that the person has allocated or will allocate adequate resources to perform the duties imposed under the Regulations. The Regulations came into operation on 1 August 2013.
Source: Full text of law
Air and operations
What permits govern backup generators and ongoing emissions?
Air Pollution Act 1987 (duty of an occupier of premises to prevent emissions)
In force
Air Pollution Act 1987 (No. 6 of 1987), section 24
Applies to both
The occupier of any premises, other than a private dwelling, must use the best practicable means to limit and, if possible, to prevent an emission from the premises. The occupier of any premises must not cause or permit an emission from the premises in such a quantity, or in such a manner, as to be a nuisance. A person who contravenes any provision of the Act, of a regulation made under it or of a notice served under it is guilty of an offence.
On conviction on indictment the fine may not exceed 500,000 euro, with a further fine not exceeding 5,000 euro for every day a continuing offence continues, and imprisonment may not exceed two years.
Source: Full text of law
EPA industrial emissions licensing (First Schedule, Class 2.1)
In force
Environmental Protection Agency Act 1992 (No. 7 of 1992), First Schedule, Class 2.1
Applies to both
Combustion installations with a total rated thermal input of 50 MW or more require an industrial emissions licence from the EPA. The Agency counts all combustion plant on a site toward that threshold, but exempts installations with large-scale emergency generation that limit operation at 50 MWth input load or more to no more than 18 hours per annum. Amazon Data Services Ireland holds industrial emissions licence P1186-01 for its facility at Clonshaugh, Dublin.
Source: Full text of law
Greenhouse gas emissions permit for combustion installations over 20 MW (emissions trading)
In force
S.I. No. 490 of 2012, European Communities (Greenhouse Gas Emissions Trading) Regulations 2012, as amended
Effective 2012-11-30 · Applies to both
Combustion of fuels in an installation with a total rated thermal input exceeding 20 MW, other than an installation for the incineration of hazardous or municipal waste, is a listed activity, and no person may carry out a listed activity at an installation except under a greenhouse gas emissions permit issued by the Environmental Protection Agency. The Agency publishes a current list of permitted installations under the Regulations as amended.
Source: Full text of law
Medium Combustion Plant Regulations 2017 (registration of plant of 1 MW to under 50 MW)
In force
S.I. No. 595 of 2017, European Union (Medium Combustion Plants) Regulations 2017
Effective 2017-12-19 · Applies to both
The Regulations apply to combustion plants with a rated thermal input of 1 MW or more and less than 50 MW, whatever fuel they use, and the Environmental Protection Agency is the competent authority. A new medium combustion plant may not be operated without being registered in the Agency's register of such plants, and an existing plant with a rated thermal input above 5 MW may not be operated unregistered from 1 January 2024.
Source: Full text of law
Public agreements
What fiscal agreements attach a data center to its host jurisdiction?
Taxes Consolidation Act 1997 (capital allowances for machinery or plant)
In force
Taxes Consolidation Act 1997 (No. 39 of 1997), sections 284 and 285A
Applies to private
Where a person carrying on a trade has incurred capital expenditure on the provision of machinery or plant for the purposes of the trade, a wear and tear allowance is made to that person for the chargeable period. The machinery or plant must belong to the person claiming and be in use for the purposes of the trade at the end of the chargeable period. A company can claim capital allowances at a rate of 12.5 percent over eight years for plant and machinery.
Under section 285A, accelerated capital allowances of 100 percent of the capital expenditure incurred on equipment on the list of energy-efficient equipment published by the Sustainable Energy Authority of Ireland can be claimed for the year in which the equipment is first used for the purposes of the trade. The scheme of accelerated capital allowances for energy-efficient equipment runs until 31 December 2030.
Source: Full text of law
02
The permitting path
Ireland's path runs grid-first: under the CRU's Large Energy Users Connection Policy (CRU/25/236, December 2025, replacing the 2021 data centre connection direction), a new connection offer requires dispatchable generation or storage matched to the facility's import capacity and a commitment to source at least 80 percent of annual demand from new Irish renewable generation within six years of energisation. Planning permission sits with the local authority in the first instance (the 2018 provision routing large data centres directly to the national planning body is not yet commenced), with appeals to An Coimisiun Pleanala, and environmental impact assessment where screening requires it. Uisce Eireann water and wastewater connections, building control certificates, and an EPA industrial emissions licence for standby fleets over 50 MW thermal complete the path.
Steps are shown in their typical order; steps at the
same stage usually run concurrently, and conditional steps apply only where
noted. Per-facility status against this path is tracked
on the Ireland record.
Every entry cites the instrument it describes.
None of it is legal advice: verify a citation before relying on it. Full
sourcing: read the methodology. The rest of the
record: all jurisdictions.