Two operating data centres granted by South Dublin County Council in January 2022, with two further buildings refused by the council but granted on appeal in July 2025 subject to a renewable-fuel generator condition.

Land use jurisdiction: South Dublin County Council

01

Measurements on record

Power

Backup generators 24 units source
02

Permitting path

Approvals on record for 1 of 11 path steps; latest: Planning permission (2025-07-31).

Ireland's path runs grid-first: under the CRU's Large Energy Users Connection Policy (CRU/25/236, December 2025, replacing the 2021 data centre connection direction), a new connection offer requires dispatchable generation or storage matched to the facility's import capacity and a commitment to source at least 80 percent of annual demand from new Irish renewable generation within six years of energisation. Planning permission sits with the local authority in the first instance (the 2018 provision routing large data centres directly to the national planning body is not yet commenced), with appeals to An Coimisiun Pleanala, and environmental impact assessment where screening requires it. Uisce Eireann water and wastewater connections, building control certificates, and an EPA industrial emissions licence for standby fleets over 50 MW thermal complete the path.

DateStepAuthorityInstrumentStatus
2022-01-19 Planning permission South Dublin County Council South Dublin County Council grant, two data centres, 21 conditions
South Dublin County Council grant, two data centres, 21 conditions
on record
2025-07-31 An Coimisiún Pleanála SDCC Reg. Ref. SD22A/0333; granted on appeal, An Coimisiun Pleanala PL06S.317802, renewable-fuel generator condition
SDCC Reg. Ref. SD22A/0333; granted on appeal, An Coimisiun Pleanala PL06S.317802, renewable-fuel generator condition (original)
on record
Grid connection application not yet requested
Connection offer and agreement not yet requested
Dispatchable generation or storage matched to import capacity
applies for new connection applications under the 2025 policy
not yet requested
Renewables matching commitment (80 percent in six years)
applies for new connection applications under the 2025 policy
not yet requested
Strategic infrastructure pre-application consultation
applies where an associated Seventh Schedule class, such as large scale onsite generation, routes the application to An Coimisiun Pleanala; the data centre specific route is not yet commenced
not yet requested
Environmental impact assessment
applies where screening determines significant effects are likely
South Dublin County Council not yet requested
Uisce Eireann wastewater connection not yet requested
Uisce Eireann water connection agreement not yet requested
Building control (commencement notice; fire safety and disability access certificates) South Dublin County Council not yet requested
EPA industrial emissions licence
applies where standby generation crosses licensing thresholds
not yet requested

Steps without a record are shown as not yet requested or not on record: absence of a record here is a records gap, not a finding about the facility. An authority shown for an empty step is the body that would issue it.

About this path and the law behind each step: law.ungovr.org/compute/ie

03

Location and sources

Lucan, South Dublin County Council, Ireland

Sources: An Coimisiun Pleanala case 317802 · DataCenterDynamics: Irish planning body approves two EdgeConneX data centers, overruling the council's refusal