Echelon Arklow Campus

under construction Campus

Operated by Echelon Data Centres

A 100 MW campus permitted by Wicklow County Council in February 2019 and upheld on appeal. EirGrid's September 2024 connection offer was the first to a large Irish data centre in over three years; construction of the first building began in 2025.

Land use jurisdiction: Wicklow County Council

01

Measurements on record

Power

Critical IT load 90 MW source
02

Permitting path

Approvals on record for 2 of 11 path steps; latest: Connection offer and agreement (2024-09-06).

Ireland's path runs grid-first: under the CRU's Large Energy Users Connection Policy (CRU/25/236, December 2025, replacing the 2021 data centre connection direction), a new connection offer requires dispatchable generation or storage matched to the facility's import capacity and a commitment to source at least 80 percent of annual demand from new Irish renewable generation within six years of energisation. Planning permission sits with the local authority in the first instance (the 2018 provision routing large data centres directly to the national planning body is not yet commenced), with appeals to An Coimisiun Pleanala, and environmental impact assessment where screening requires it. Uisce Eireann water and wastewater connections, building control certificates, and an EPA industrial emissions licence for standby fleets over 50 MW thermal complete the path.

DateStepAuthorityInstrumentStatus
2019-02-19 Planning permission An Coimisiún Pleanála Wicklow County Council grant (February 2019); appeal dismissed by An Bord Pleanala
Wicklow County Council grant (February 2019); appeal dismissed by An Bord Pleanala
on record
2024-09-06 Connection offer and agreement EirGrid EirGrid grid connection offer, Arklow campus
EirGrid grid connection offer, Arklow campus (original)
on record
Grid connection application not yet requested
Dispatchable generation or storage matched to import capacity
applies for new connection applications under the 2025 policy
not yet requested
Renewables matching commitment (80 percent in six years)
applies for new connection applications under the 2025 policy
not yet requested
Strategic infrastructure pre-application consultation
applies where an associated Seventh Schedule class, such as large scale onsite generation, routes the application to An Coimisiun Pleanala; the data centre specific route is not yet commenced
not yet requested
Environmental impact assessment
applies where screening determines significant effects are likely
Wicklow County Council not yet requested
Uisce Eireann wastewater connection not yet requested
Uisce Eireann water connection agreement not yet requested
Building control (commencement notice; fire safety and disability access certificates) Wicklow County Council not yet requested
EPA industrial emissions licence
applies where standby generation crosses licensing thresholds
Environmental Protection Agency Crag Arklow Limited IE licence application
Crag Arklow Limited IE licence application (original)
pending

Steps without a record are shown as not yet requested or not on record: absence of a record here is a records gap, not a finding about the facility. An authority shown for an empty step is the body that would issue it.

About this path and the law behind each step: law.ungovr.org/compute/ie

03

Location and sources

Arklow, Wicklow County Council, Ireland

Sources: RTE: Permission granted for Arklow data centre · Irish Times: Echelon secures grid connection for Wicklow data centre · EPA: Crag Arklow Limited licence application

Every record links to its source: openly licensed datasets (Epoch AI, CC BY; Wikidata, CC0; US EPA, public domain) and public permit records. Full sourcing and licensing: methodology · sources.