Art Data Centres Campus Ennis

approved Campus

Operated by Art Data Centres

A six-hall campus at Tooreen on the Tulla Road, granted by Clare County Council in August 2022 and confirmed on appeal by An Coimisiun Pleanala in April 2024 with revised conditions; a judicial review challenge was dismissed, with leave to appeal refused in June 2026.

Land use jurisdiction: Clare County Council

01

Measurements on record

No disclosed measurements on record yet.

02

Permitting path

Approvals on record for 2 of 11 path steps; latest: Planning permission (2024-04-05).

Ireland's path runs grid-first: under the CRU's Large Energy Users Connection Policy (CRU/25/236, December 2025, replacing the 2021 data centre connection direction), a new connection offer requires dispatchable generation or storage matched to the facility's import capacity and a commitment to source at least 80 percent of annual demand from new Irish renewable generation within six years of energisation. Planning permission sits with the local authority in the first instance (the 2018 provision routing large data centres directly to the national planning body is not yet commenced), with appeals to An Coimisiun Pleanala, and environmental impact assessment where screening requires it. Uisce Eireann water and wastewater connections, building control certificates, and an EPA industrial emissions licence for standby fleets over 50 MW thermal complete the path.

DateStepAuthorityInstrumentStatus
2022-08-08 Planning permission Clare County Council Clare County Council Planning Ref. 21/757, granted 8 August 2022
Clare County Council Planning Ref. 21/757, granted 8 August 2022 (original)
on record
2024-04-05 An Coimisiún Pleanála An Coimisiun Pleanala PL03.314474, permission with revised conditions
An Coimisiun Pleanala PL03.314474, permission with revised conditions (original)
on record
Grid connection application not yet requested
Connection offer and agreement not yet requested
Dispatchable generation or storage matched to import capacity
applies for new connection applications under the 2025 policy
not yet requested
Renewables matching commitment (80 percent in six years)
applies for new connection applications under the 2025 policy
not yet requested
Strategic infrastructure pre-application consultation
applies where an associated Seventh Schedule class, such as large scale onsite generation, routes the application to An Coimisiun Pleanala; the data centre specific route is not yet commenced
not yet requested
Environmental impact assessment
applies where screening determines significant effects are likely
An Coimisiún Pleanála Environmental impact assessment report and Natura impact statement with PL03.314474
Environmental impact assessment report and Natura impact statement with PL03.314474 (original)
on record
Uisce Eireann wastewater connection not yet requested
Uisce Eireann water connection agreement not yet requested
Building control (commencement notice; fire safety and disability access certificates) Clare County Council not yet requested
EPA industrial emissions licence
applies where standby generation crosses licensing thresholds
not yet requested

Steps without a record are shown as not yet requested or not on record: absence of a record here is a records gap, not a finding about the facility. An authority shown for an empty step is the body that would issue it.

About this path and the law behind each step: law.ungovr.org/compute/ie

03

Location and sources

Ennis, Clare County Council, Ireland

Sources: An Coimisiun Pleanala case 314474 · Clare County Council: Council welcomes decision to grant planning permission for Data Centre Campus · Irish Times: High Court green light for Ennis data centre as leave to appeal is refused

Every record links to its source: openly licensed datasets (Epoch AI, CC BY; Wikidata, CC0; US EPA, public domain) and public permit records. Full sourcing and licensing: methodology · sources.