Data-center law in Virginia

Subnational jurisdiction · as of 2026-11-02

Drafted with AI

Drafted with AI from the cited sources under the direction of UnGovr staff. UnGovr holds editorial responsibility for this page. How this site is made

Virginia's data-center permitting spine runs through county land-use case records: rezonings and special use permits under the zoning enabling statutes, then building permits under the Uniform Statewide Building Code, stormwater coverage under the Virginia Stormwater Management Program, and DEQ air permits for generator fleets, which DEQ publishes in a data-center permit register.

Virginia also carries the country's most consequential data-center incentive, the retail sales and use tax exemption for qualifying data-center equipment, which conditions eligibility on capital investment and job thresholds.

Section 15.2-2209.5 of the Code of Virginia now requires a locality to obtain a site assessment of the sound profile on homes and schools within 500 feet, and a form from the serving utility describing the substations and transmission voltage, before approving a rezoning, special exception, or special use permit for a new facility the applicant reasonably anticipates will need 100 megawatts or more from the electric utility providing it retail service.

The section does not apply to an expansion or modification of an already existing or approved facility, on a site that already holds an approval, of no more than an additional 100 megawatts.

Enactment 3 of chapter 1123 of the 2026 Acts of Assembly directs the State Corporation Commission, in a biennial review of a Phase II Utility, to take all measures to reasonably ensure that customers with a demand of 25 megawatts or greater and an annual load factor of 75 percent or greater are not subsidized by other customers and do not adversely impact those customers' approved rates.

Section 56-596.7 of the Code of Virginia requires each Phase I and Phase II Utility to file, by January 15, 2027, a petition for approval of a voluntary demand flexibility program that applies to high energy demand customers.

Subdivision 4 of section 56-598 of the Code of Virginia requires an integrated resource plan to include at least one modeling scenario that exceeds the energy savings targets through measures that include known data center efficiency efforts and innovative data center tariffs approved by the Commission or offsetting investments in offsite energy efficiency upgrades.

From January 1, 2027, section 62.1-44.38 of the Code of Virginia requires a water user registering withdrawal data that provides water offsite to report the monthly volumes of potable water and, reported separately, of reclaimed water provided to a data center.

Section 10.1-1322.6 of the Code of Virginia bars the Department from issuing a permit on a data center application submitted on or after July 1, 2026 unless each engine-generator set limit is equal to or less than the emissions achieved by a Tier 4 equivalent set.

Subdivision 19 c of section 58.1-609.3 of the Code of Virginia lets a data center operator with a qualifying memorandum of understanding continue the data center sales and use tax exemption through June 30, 2040 if it invests at least $35 billion and creates at least 1,000 new full-time jobs.

Subdivision A 43 of section 58.1-3506 of the Code of Virginia lists computer equipment and peripherals used in a data center among the items of property declared to be separate classes of tangible personal property.

Section 58.1-3295.3 of the Code of Virginia requires fixtures installed at a data center and taxed under the chapter to be assessed using the cost approach.

Section 58.1-422.2 of the Code of Virginia apportions the Virginia taxable income of a taxpayer with enterprise data center operations by multiplying the income by the sales factor from July 1, 2017.

Section 59.1-284.42 of the Code of Virginia creates the Cloud Computing Cluster Infrastructure Grant Fund, a special nonreverting fund in the state treasury.

Item 3-5.24 of the 2026 Special Session I budget act imposes an electricity consumption tax of $0.011 per kilowatt hour on every data center operator for electricity consumed at each data center, from July 1, 2026 until July 1, 2028.

Executive Order 22 of 2026 bars the Virginia Economic Development Partnership from providing assistance through the Virginia Business Ready Sites Program, any expedited permitting program, or any similar discretionary state program for a new data center project with an anticipated peak electrical demand of 25 MW or greater.

01

Instruments on record

19 instruments on record, grouped by the family of approval each one governs.

Land use

Who decides whether a data center may occupy a site, and through what approval?

Siting of data centers: site assessment before a rezoning, special exception or special use permit for a high energy use facility

In force

Va. Code 15.2-2209.5

Effective 2026-07-01 · Applies to both

Before a locality approves a rezoning application, special exception or special use permit for the siting of a new high energy use facility, it must require the applicant to perform and submit a site assessment of the sound profile of the facility on residential units and schools located within 500 feet of the facility property boundary.

A high energy use facility is a facility that an applicant reasonably anticipates, at the time of filing, will require 100 megawatts or more of electrical power from an electric utility providing retail service to the facility. A locality may also require the site assessment to examine the effect of the proposed facility on ground and surface water resources, agricultural resources, parks, registered historic sites, and forestland on the facility site or immediately contiguous land.

Before the same approval, the locality must require the electric utility providing retail service to the new facility to submit a form describing any new or existing substations that will serve the facility and the anticipated transmission voltage required, to the extent known and practicable.

The locality uses the submitted assessments to assess consistency with the policies of its comprehensive plan, if any, and compliance with its adopted noise ordinances, zoning ordinance provisions, and other applicable laws and regulations, if any.

The section does not apply to a site with an existing legislative or administrative approval where the applicant is seeking an expansion or modification of an already existing or approved facility and the expansion does not exceed an additional 100 megawatts or more of electrical power. The section does not change or delegate any authority or jurisdiction of the State Corporation Commission, and does not prohibit, limit, or supersede existing local zoning authority.

Source: Full text of law

Special use permits and site plans (enabling statute)

In force

Va. Code 15.2-2286

Applies to both

Authorizes localities to require special use permits and site plan approval; where a district's zoning allows data centers by special exception, this is the enabling authority for that case record.

In a county with a zoning ordinance, a petition to amend the zoning ordinance or map must be decided within a reasonable time not exceeding 12 months, unless the applicant requests or consents to a longer period or withdraws it. An ordinance may require Phase I environmental site assessments, and Phase II assessments where the Phase I findings make them reasonably necessary, and may require disclosure and remediation of contamination before approval of subdivision and development plans.

An ordinance may make a zoning violation a misdemeanor punishable by a fine of up to $1,000, with separate fines rising to up to $2,000 for each 10-day period a violator fails to abate it after the court's deadline.

Source: Full text of law

Zoning and rezoning (enabling statute)

In force

Va. Code 15.2-2285

Applies to both

Governs adoption and amendment of local zoning ordinances and maps. Data-center rezonings, including the proffered conditions that often carry the project's public commitments, proceed under this section.

A proposed zoning amendment must be referred to the local planning commission, which holds a public hearing, and a commission that has not reported within 100 days after its first meeting on the referral, or a shorter period the governing body sets, is deemed to have approved it unless the applicant has withdrawn it.

The governing body must also hold a public hearing, and an additional one if land would be zoned to a more intensive use classification than the documentation made available for examination. Any action contesting a decision to adopt or refuse a zoning amendment, or to grant or refuse a special exception, must be filed in circuit court within 30 days of the decision, a requirement the statute makes mandatory and jurisdictional.

Source: Full text of law

Energy and grid

What authorizations govern grid connection and onsite generation?

Data Center Electricity Consumption Tax

In force

2026 Va. Acts, Sp. Sess. I, ch. 1, Item 3-5.24

Effective 2026-07-01 · Applies to private

Beginning on and after July 1, 2026 but before July 1, 2028, an electricity consumption tax at the rate of $0.011 per kilowatt hour is imposed on every data center operator for all electricity consumed at each data center per month. The data center electricity consumption tax applies whether the electricity is provided through an incumbent electric utility, an incumbent electric cooperative, or a competitive service provider, or is self-supplied.

The State Corporation Commission collects the data center electricity consumption tax monthly. A supplier lists the tax as a separate line item on the operator's invoice, and an operator that self-supplies electricity remits the tax directly to the Commission on a monthly return.

No more than $600,000,000 of the revenue in a fiscal year is deposited to the general fund. Tax revenue above that amount, less the Commission's administrative costs, is deposited to a special nonreverting fund that pays refunds to operators, in proportion to their share of collections, in fiscal years beginning on and after July 1, 2027. A data center does not include a facility whose primary function is to facilitate the provision of internet access service or a communication service.

Source: Full text of law

Demand flexibility programs for high energy demand customers

In force

Va. Code 56-596.7

Applies to both

Each Phase I and Phase II Utility must file a petition with the Commission by January 15, 2027 for approval of a voluntary demand flexibility program that applies to high energy demand customers, and the Commission must issue a final order on the petitions no later than November 30, 2027.

A high energy demand customer is a retail electric service customer with a contracted or measured electric demand of 25 megawatts or greater and an anticipated or measured average annual electric load factor of 75 percent or greater, other than a contracted defense facility.

Participation by a high energy demand customer in a demand flexibility program is voluntary. For each demand flexibility program, the Commission sets a demand flexibility standard, which the utility, working with its high energy demand customers, must make best, reasonable efforts to meet or exceed annually, and carbon-emitting generating resources are ineligible for participation.

Any incentive must be designed to encourage participation without unreasonably shifting program costs onto other retail electric service customers.

Each cooperative that serves one or more high energy demand customers must establish a voluntary program by January 1, 2029, after a technical work group it convenes reports to the Commission by September 30, 2027. The Commission reports on the status and performance of the programs by September 1, 2028 and annually after that.

Source: Full text of law

High-load electric customers: cost allocation and rate-schedule election

In force

Fair and Affordable Electric Rates and Reliability Act, 2026 Va. Acts ch. 1123, enactments 3 and 4

Applies to both

In a biennial review of a Phase II Utility, the State Corporation Commission must take all measures to reasonably ensure that customers with a contracted or measured demand of 25 megawatts or greater and an annual load factor of 75 percent or greater are not subsidized by other customers, and that other customers' approved rates are not adversely impacted by that service.

A customer of a Phase II Utility with at least 200 full-time-equivalent employees in manufacturing, industrial, or consumer goods warehousing and distribution work other than data storage could elect, by notice on or before July 1, 2026, to stay on its existing default rate schedule. That election is one-time and cannot be revoked before December 31, 2033.

Source: Full text of law

Integrated resource plan contents: scenario with data center efficiency and tariffs

In force

Va. Code 56-598(4)

Applies to both

An electric utility's integrated resource plan must include only modeling scenarios that meet the total energy savings targets required by subsection B of section 56-596.2. An integrated resource plan must also include at least one modeling scenario, consistent with section 56-585.5, that exceeds those targets through a listed set of measures.

The listed measures for that scenario include known data center efficiency efforts and innovative data center tariffs approved by the Commission or offsetting investments in offsite energy efficiency upgrades, alongside energy efficiency upgrades to homes and businesses, dynamic pricing, battery storage, transmission line upgrades, grid-enhancing technology, virtual power plants, managed electric vehicle charging and home and business electrification.

Source: Full text of law

Water and utilities

Who commits water and sewer service, and under what assessment?

Water withdrawal and use registration: volumes provided to data centers, from January 1, 2027

Enacted, not yet in force

Va. Code 62.1-44.38(C)

Effective 2027-01-01 · Applies to both

From January 1, 2027, a water user that the Board requires by regulation to register its water withdrawal and use data, and that provides water to another person offsite, must include in its report the total volume of potable water and, reported separately, the total volume of reclaimed water provided during each month to a data center with an air permit issued by the Department. Where monthly data is not available, the data may be submitted based on the total volumes provided during each quarter.

Reclaimed water volumes may not be aggregated with potable water volumes in any public reporting, summary, or planning document the Board produces under section 62.1-44.38. The Board may require registration where a withdrawal exceeds one million gallons in any single month for crop irrigation, or where the daily average during any single month exceeds 10,000 gallons per day for any other user.

Source: Full text of law

Construction

What codes and permits govern the build itself?

Uniform Statewide Building Code

In force

Va. Code 36-97 et seq.

Applies to both

The statewide building code administered by local building officials; the building permit for the structure issues under it.

Source: Full text of law

Virginia Stormwater Management Program (construction)

In force

Va. Code 62.1-44.15:24 et seq.

Applies to both

Land disturbance of one acre or more, or of less than one acre within a larger common plan of development or sale that ultimately disturbs one or more acres, requires construction general permit coverage and approval from the local Erosion and Sediment Control Program (from DEQ for state and federal projects). The program authority is the Board or a locality the Board approves to operate the program.

For new development projects, the limit on total phosphorus load under 9VAC25-875-580 changed from 0.41 to 0.26 pounds per acre per year effective July 1, 2025.

Source: Full text of law

Air and operations

What permits govern backup generators and ongoing emissions?

Air permits for data centers: Tier 4 equivalent limits for engine-generator sets

In force

Va. Code 10.1-1322.6

Effective 2026-07-01 · Applies to both

For any application submitted for a data center on or after July 1, 2026 for a permit issued by the Department under the chapter, including coverage under a general permit, the Department may not issue the permit unless the emission limit for each engine-generator set the permit establishes is equal to or less than the emissions achieved by a Tier 4 equivalent set.

A Tier 4 equivalent set has a selective catalytic reduction system or equivalent for nitrogen oxides control, a diesel oxidation catalyst system or equivalent for carbon monoxide control, and a diesel particulate filter or equivalent for particulate matter control. Section 10.1-1322.6 does not prevent the Department from determining best available control technology or from setting more stringent emission limits in a permit.

Source: Full text of law

Air permitting for new and modified sources

In force

Va. Code 10.1-1308; 9VAC5-80

Applies to both

DEQ permits stationary sources under the State Air Pollution Control Board's regulations; data-center generator fleets permit under the new and modified source rules, and DEQ publishes a register of data-center air permits with equipment lists.

Source: Full text of law

Public agreements

What fiscal agreements attach a data center to its host jurisdiction?

Cloud Computing Cluster Infrastructure Grant Fund

In force

Va. Code 59.1-284.42

Applies to both

Section 59.1-284.42 creates in the state treasury a special nonreverting fund that pays grants to a qualified company to pay or reimburse infrastructure costs for the construction and support of data center facilities and costs for workforce development, recruiting, and training.

A qualified company is a company that, after qualification, enters into a memorandum of understanding and is expected by the performance date to make a capital investment of at least $50 billion and to create at least 1,500 new full-time jobs paying an average annual wage of at least one and one-half times the prevailing wage of the locality. Qualification requires an endorsement by the MEI Project Approval Commission and approval by the General Assembly in a general appropriation act.

Capital investments and new full-time jobs in a locality that is not identified in the memorandum of understanding or has not entered into a performance agreement do not qualify for grant payments. The local match is the funds a locality commits to the qualified company, and it must be at least twice the amount provided from the Fund.

Grant payments are made for fiscal years from the one starting July 1, 2025 through the one starting July 1, 2044, subject to appropriation, and the total paid may not exceed the amount the General Assembly approved.

Source: Full text of law

Computer equipment and peripherals used in a data center: separate class of tangible personal property

In force

Va. Code 58.1-3506(A)(43)

Applies to both

Computer equipment and peripherals used in a data center are declared a separate class of property and constitute a classification for local taxation separate from other classifications of tangible personal property provided in the chapter.

For this purpose a data center is a facility whose primary services are the storage, management, and processing of digital data and that is used to house computer and network systems, systems for monitoring and managing infrastructure performance, equipment used for the transformation, transmission, distribution, or management of at least one megawatt of capacity of electrical power and cooling, Internet-related equipment and services, data communications connections, environmental controls, fire protection systems, and security systems and services.

Source: Full text of law

Data center retail sales and use tax exemption

In force

Va. Code 58.1-609.3(18)

Effective 2010-07-01 · Applies to private

Exempts from retail sales and use tax computer equipment and enabling software, bought or leased for use in a qualifying data center, including servers, routers, chillers and backup generators used in operating the exempt equipment, from July 1, 2010 through June 30, 2035. General building improvements and other fixtures are not exempt. The exemption is Virginia's principal data-center incentive and the eligibility agreements sit with VEDP.

A data center qualifies if it is in a Virginia locality, results in new capital investment of at least $150 million on or after January 1, 2009, and results in at least 50 new jobs paying at least one and one-half times the prevailing average wage in the locality. In a distressed locality the thresholds fall to $70 million and 10 jobs. The operator and its tenants may claim the exemption and meet the thresholds collectively.

Before claiming, the claimant must enter a memorandum of understanding with VEDP that sets the investment and job goals, the timeline and the repayment obligations if the goals are missed, and the operator must file an annual report with VEDP covering employment, investment, wages, qualifying expenses and tax benefit.

An operator that signed a memorandum of understanding on or after January 1, 2023 may extend the exemption through June 30, 2040 by investing at least $35 billion and creating at least 1,000 new full-time jobs, and through June 30, 2050 by investing at least $100 billion in total and creating at least 2,500 new full-time jobs, in each case with at least 100 of those jobs paying one and one-half times the Commonwealth's prevailing average wage.

Source: Full text of law

Data center retail sales and use tax exemption: extension through 2040 and 2050

In force

Va. Code 58.1-609.3(19)

Applies to private

A data center operator that enters into a memorandum of understanding with the Virginia Economic Development Partnership Authority on or after January 1, 2023 may extend the exemption in subdivision 18 for computer equipment and enabling software bought or leased for data centers under common ownership or affiliation with the operator.

If on or after January 1, 2023 but before July 1, 2035 the operator makes a capital investment of at least $35 billion in data centers in the localities the memorandum identifies and creates at least 1,000 new full-time jobs, at least 100 of which pay at least one and one-half times the prevailing average wage in the Commonwealth, the exemption continues through June 30, 2040.

If on or after January 1, 2023 but before July 1, 2040 the operator makes a total capital investment of at least $100 billion and creates a total of at least 2,500 new full-time jobs, at least 100 of which pay at least one and one-half times the prevailing average wage in the Commonwealth, the exemption continues through June 30, 2050.

The exemption extension in subdivision 19 also covers equipment bought or leased to upgrade, supplement, or replace equipment bought or leased in the initial investment.

Source: Full text of law

Executive order implementing the Virginia Data Center Accountability Framework

In force

Virginia Executive Order No. 22 (2026)

Effective 2026-09-18 · Applies to government

Designates the Office of the Chief Energy Officer as the lead for coordinating a unified statewide approach to the Virginia Data Center Accountability Framework, and requires all Secretariats and executive branch agencies to coordinate with and support it on request.

Effective upon issuance, the Virginia Economic Development Partnership may not provide assistance through the Virginia Business Ready Sites Program, any expedited permitting program, or any similar discretionary state economic development, site-readiness, or expedited review program for a new data center project with an anticipated peak electrical demand of 25 MW or greater.

No executive branch agency, department, board, commission, authority or employee under the Governor's supervision may enter into, enforce or require a nondisclosure agreement that prevents public disclosure of material information concerning a proposed commercial data center development, its public incentives, anticipated resource demands, or its potential community impacts.

The Department of Environmental Quality must prioritize and expedite data-center noise regulations, and must conduct or oversee a cumulative-impact review of diesel and other backup generation at data centers, with findings and recommendations to the Governor's office within 180 days.

The Department of Environmental Quality must also prioritize regulations establishing criteria for cooling water scarcity areas, and the Eastern Virginia Groundwater Management Area is designated a cooling water scarcity area.

The Office of the Chief Energy Officer must publish an initial Data Center Planning and Community Engagement Toolkit for local governments and communities within 120 days, and must submit proposed designation criteria for a Virginia Local Energy and Accountable Data Centers program by the end of calendar year 2027.

Source: Full text of law

Income tax apportionment for taxpayers with enterprise data center operations

In force

Va. Code 58.1-422.2

Applies to private

For taxable years beginning on or after July 1, 2016, the Virginia taxable income of a taxpayer with enterprise data center operations, excluding income allocable under section 58.1-407, is apportioned within and without the Commonwealth, and from July 1, 2017 the apportionment is made by multiplying the income by the sales factor.

The enterprise data center apportionment formula applies only to a taxpayer that entered into a memorandum of understanding with the Virginia Economic Development Partnership Authority on or after July 1, 2015 to make a new capital investment of at least $150 million in an enterprise data center in the Commonwealth, beginning with the taxable year for which the Authority certifies in writing that the investment has been completed.

Enterprise data center operations are operations that house information technology equipment, manage and process digital data to provide application services, are developed and owned by the taxpayer, and are operated by the taxpayer or its affiliates substantially for their own use.

Source: Full text of law

Real property assessment: data center fixtures assessed by the cost approach

In force

Va. Code 58.1-3295.3

Applies to both

If fixtures are installed at a data center and taxed under the chapter, the fixtures must be assessed using the cost approach, which assesses value by determining the cost to construct a reproduction or suitable replacement of the fixtures and deducting physical, functional, and economic depreciation.

Fixtures means all fixtures and equipment used in a data center except computer equipment and peripherals, equipment used for external surveillance and security, and fire and burglar alarm systems.

Fixtures includes generators, radiators, exhaust fans, fuel storage tanks, electrical substations, power distribution equipment, cogeneration equipment, batteries, chillers, computer room air conditioners, cool towers, heating, ventilating, and air conditioning systems, water storage tanks, water pumps, piping, monitoring systems, and transmission and distribution equipment.

Source: Full text of law

02

The permitting path

Virginia's sequence runs through county land-use case records to DEQ air permits; rezonings and special use permits are the public record spine, and DEQ publishes the data-center air permit register.

# Step Authority level Legal basis
1 Site control (deed or lease) local Va. Code 55.1-600 (writings recorded with the circuit court clerk); land-use applications require the owner's authorization
2 Special use permit / site plan local Va. Code 15.2-2286
3 Rezoning
applies where the site's zoning does not already allow the use
local Va. Code 15.2-2285
4 Natural gas service
applies where the facility uses natural gas
utility Serving gas utility tariff
5 Utility interconnection (PJM queue) utility Serving utility tariff; PJM interconnection for transmission-level service
6 Sewer service commitment utility Serving sanitation authority
7 Water service commitment utility Serving water authority
8 Building permit local Virginia Uniform Statewide Building Code
9 Stormwater (VSMP permit)
applies where land disturbance passes permit thresholds
regulator Virginia Stormwater Management Program construction permit
10 DEQ air permit (generators) regulator 9VAC5-80 minor new source review
11 Public agreements and incentives
applies where negotiated with the host jurisdiction
local Local incentive and siting agreements

Steps are shown in their typical order; steps at the same stage usually run concurrently, and conditional steps apply only where noted. Per-facility status against this path is tracked on the Virginia record.

Every entry cites the instrument it describes. None of it is legal advice: verify a citation before relying on it. Full sourcing: read the methodology. The rest of the record: all jurisdictions.