Data-center law in Mexico

National jurisdiction · as of 2026-09-07

Mexico has no data-centre-specific statute; a data centre's own or backup electricity generation and its construction fall within two general federal regimes.

The Ley del Sector Eléctrico (LSE), an entirely new law in force since 18 March 2025 replacing the 2014 Ley de la Industria Eléctrica, requires a generation permit from the Comisión Nacional de Energía (CNE) for any electric plant with 0.7 MW or more of installed capacity, backed by a sanctions regime running from fixed Unidad de Medida y Actualización (UMA) multiples to a percentage of the infractor's gross annual income.

The Ley General del Equilibrio Ecológico y la Protección al Ambiente (LGEEPA) requires prior federal environmental-impact authorisation before a listed project, including the electric industry generally, may proceed. Construction permitting is issued by state or municipal authorities in Mexico rather than under a federal building-authorisation statute, and foreign-investment clearance under the Ley de Inversión Extranjera carries no data-centre-specific rule.

No post-2019 federal special-economic-zone or Polo de Bienestar statute currently exists; the 2016 Ley de Zonas Económicas Especiales was repealed in 2019 and is history rather than current law.

01

Instruments on record

2 instruments on record, grouped by the family of approval each one governs.

Environmental review

What impact review must precede approval, and who leads it?

Ley General del Equilibrio Ecológico y la Protección al Ambiente, Environmental Impact Assessment for Electric-Industry Projects

In force

Ley General del Equilibrio Ecológico y la Protección al Ambiente (LGEEPA), art. 28

Applies to both

Article 28 requires a person who intends to carry out a listed work or activity to obtain the Secretaría's prior environmental-impact authorisation. The listed categories include, at fracción II, the electric industry generally alongside petroleum, petrochemical, chemical, steel, paper, sugar, and cement industries, so an electric-generation facility built for a data centre's own supply falls within this category regardless of size.

Fracción XIII is a residual category reaching any federally-competent work or activity that could cause serious and irreparable ecological imbalance, harm to public health or ecosystems, or exceed the limits set by applicable environmental-protection provisions.

Article 171 backs the authorisation regime with an administrative fine of 30 to 50,000 days of the general minimum wage in effect when the sanction is imposed, temporary or permanent closure, administrative arrest of up to 36 hours, and suspension or revocation of the permit or authorisation, among other sanctions the Secretaría may impose.

The law does not name a data centre specifically; the electric-industry category at fracción II reaches a data centre's own generation or cogeneration installation without regard to its capacity.

Source: Full text of law

Energy and grid

What authorizations govern grid connection and onsite generation?

Ley del Sector Eléctrico, Generation Licensing and Penalty Regime

In force

Ley del Sector Eléctrico (LSE) Nueva Ley publicada en el Diario Oficial de la Federación el 18 de marzo de 2025, arts. 16 a 19, 30, 184 a 188

Effective 2025-03-19 · Applies to both

Article 16 lets the State, private parties, or a mixed-investment scheme generate electricity. Article 17 organises generation into distributed generation, self-consumption (autoconsumo), and generation for the wholesale electricity market. Article 19 requires every electric plant with installed capacity of 0.7 MW or more to hold a valid generation permit issued by the Comisión Nacional de Energía (CNE); a plant below that threshold is an exempt generator and needs no generation permit.

Article 30 defines self-consumption as electricity a plant of 0.7 MW or more produces to meet the on-site needs of the permit holder, which is the category a data centre installing its own generation or backup capacity would fall into once it reaches that threshold.

Article 184 sets the sanctions regime: infractions such as obstructing CENACE's instructions or breaching accounting-separation duties draw a fine of 10 percent of the infractor's gross income in the prior year; other listed infractions draw fines expressed in multiples of the Unidad de Medida y Actualización (UMA), for example 128,000 to 514,000 UMA for failing to timely provide required information, and 26,000 to 128,000 UMA for wrongfully suspending electricity supply to a final user.

Article 187 fines any other infraction not otherwise listed with 1,000 to 10,000 UMA. Article 188 lets the CNE revoke a permit in addition to imposing a fine.

Source: Full text of law