Data-center law in Hong Kong

National jurisdiction · as of 2026-11-02

Drafted with AI

Drafted with AI from the cited sources under the direction of UnGovr staff. UnGovr holds editorial responsibility for this page. How this site is made

Hong Kong has no statute on the siting or utility supply of data centres as such, apart from the Buildings Energy Efficiency Ordinance, Cap. 610, which since 20 September 2026 treats a building or a part of an industrial building occupied principally as a data centre as a prescribed and audited building.

Every other family is filled by general law a data-centre build must clear: the Town Planning Ordinance for land use, the Environmental Impact Assessment Ordinance for the power plants and substations Schedule 2 lists, the Water Pollution Control Ordinance for discharges, the Air Pollution Control Ordinance for fossil-fuel electricity works above 5 MW, and the Electricity Ordinance for registering and maintaining generating facilities, including standby ones, where a facility that only supplies its owner's own installation, or forms part of an installation needing a periodic test certificate, is exempt from registration but not from the maintenance duty.

No ordinance or regulation other than Cap. 610 uses the term data centre as a rule of law, so a data centre reaches the general ordinances only through the plant, discharge or development it involves, and no statute grants a concession or incentive that names one.

01

Instruments on record

6 instruments on record, grouped by the family of approval each one governs.

Land use

Who decides whether a data center may occupy a site, and through what approval?

Town Planning Ordinance, Planning Permission and Unauthorized Development

In force

Town Planning Ordinance (Cap. 131), ss. 4, 16 and 21

Applies to private

A draft plan may show zones or districts set apart for use for residential, commercial, industrial or other specified uses. Where a plan provides for the grant of permission for any purpose, an application for the grant of that permission must be made to the Board.

Under section 21, added by Ordinance 4 of 1991, while a plan of a development permission area is effective a person must not undertake or continue development in the area unless it is an existing use, is permitted under the latest plan, or permission has been granted under section 16. A person who contravenes that prohibition is liable to a fine of 500,000 dollars on a first conviction and 1,000,000 dollars on a second or subsequent conviction. The Ordinance commenced on 23 June 1939; section 21 was added to it later.

Source: Full text of law

Environmental review

What impact review must precede approval, and who leads it?

Environmental Impact Assessment Ordinance, Designated Projects and Environmental Permits

In force

Environmental Impact Assessment Ordinance (Cap. 499), ss. 5, 9 and 26 and Schedule 2

Effective 1998-04-01 · Applies to both

A person must not construct or operate a designated project listed in Part I of Schedule 2, or decommission one listed in Part II, without an environmental permit or contrary to its conditions. A person planning a designated project applies to the Director for an environmental impact assessment study brief, or for approval to apply directly for an environmental permit.

Schedule 2 lists an electricity power plant running on fossil fuel with a production capacity of more than 100 megawatts as a designated project. Schedule 2 also lists a 400 kV electricity substation and transmission line.

A contravention of section 9 is punishable on a first conviction on indictment by a fine of 2,000,000 dollars and imprisonment for 6 months, and on a second or subsequent conviction on indictment by a fine of 5,000,000 dollars and imprisonment for 2 years, with a fine of 10,000 dollars for each day a continuing offence goes on. An action taken in response to an emergency and in the interests of public safety or public health is not an offence. The Ordinance commenced on 1 April 1998.

Source: Full text of law

Energy and grid

What authorizations govern grid connection and onsite generation?

Electricity Ordinance, Generating Facility Registration

In force

Electricity Ordinance (Cap. 406), ss. 21, 22 and 55

Effective 1990-11-02 · Applies to private

The owner of a generating facility that is in use or on standby use must register it with the Director, unless a listed exception applies. No person may use an unregistered generating facility that is required to be registered. The registration duty does not apply to a facility that forms part of an electrical installation requiring a periodic test certificate, or that only supplies electricity to an installation owned by the facility's owner.

The owner of a registered generating facility, and the owner of a facility exempt from registration on either of those grounds, must maintain it in continuous safe working order. A contravention of section 21(1), (3) or (4) or section 22 is an offence, and a person who commits an offence under section 55 is liable to a fine at level 3. The Ordinance commenced on 2 November 1990.

Source: Full text of law

Water and utilities

Who commits water and sewer service, and under what assessment?

Water Pollution Control Ordinance, Discharges into Water Control Zones

In force

Water Pollution Control Ordinance (Cap. 358), ss. 7, 8, 9, 11 and 12

Applies to both

A person commits an offence who discharges any waste or polluting matter into the waters of Hong Kong in a water control zone, or who discharges any matter other than domestic sewage into a communal sewer or communal drain in a water control zone (section 9). The Ordinance commenced on 1 April 1981, but the prohibition applies to a new discharge only from the day the Chief Executive appoints by order for the zone.

It is a defence that the discharge is made under, and in accordance with, a licence granted under section 20. An offence under section 8(1) or 9(1) is punishable by imprisonment for 6 months and a fine of 200,000 dollars for a first offence and 400,000 dollars for a second or subsequent offence, plus 10,000 dollars for each day a continuing offence goes on.

Discharging poisonous or noxious matter carries a fine of 400,000 dollars and imprisonment for 1 year for a first offence, and 1,000,000 dollars and imprisonment for 2 years for a second or subsequent offence.

Source: Full text of law

Construction

What codes and permits govern the build itself?

Buildings Energy Efficiency Ordinance, Data Centre Provisions

In force

Buildings Energy Efficiency Ordinance (Cap. 610), ss. 2, 7, 8, 21 and 22 and Schedules 1, 4, 5 and 6, as amended by Ordinance 24 of 2025

Effective 2026-09-20 · Applies to both

The Buildings Energy Efficiency Ordinance defines a data centre as a place for housing and operating computer systems, servers, telecommunications equipment and associated support components in a secure and controlled environment principally for providing data storage, data processing and data distribution services. A building occupied principally as a data centre, and a portion of an industrial building so occupied, are prescribed buildings in Schedule 1.

Part 2 of the Ordinance applies to such a building only where consent to the commencement of building works for superstructure construction is given after the relevant date. The developer must submit a stage one declaration within 2 months after that consent is given, and a developer who fails to do so is liable to a fine of $500,000 and a further $10,000 for each day the offence continues.

The owner of a building must cause an energy audit of its central building services installations at the intervals Schedule 5 specifies. Schedule 4 lists a building occupied principally as a data centre, and a portion of an industrial building so occupied. For a data centre in a portion of an industrial building that starts operation on or after the relevant date, the first energy audit is due 5 years after the date the data centre starts operation.

A data centre in such a portion that started operation before the relevant date must have its first energy audit within 1 year after the relevant date. A building occupied principally as a data centre takes its first energy audit on the timetable in Parts 3 and 5 of Schedule 6, and for both kinds of data centre each later energy audit is due within 5 years after the preceding one.

Part 4 does not apply to a building if the head of a Government department advises the Director in writing that an energy audit would be contrary to the interests of national security. The registered energy assessor sends the Director a Data Disclosure Form for publishing the technical information contained in the energy audit report. An owner of a building who contravenes the energy audit requirement commits an offence and is liable on conviction to a fine at level 5. The data centre provisions came into operation on 20 September 2026.

Source: Full text of law

Air and operations

What permits govern backup generators and ongoing emissions?

Air Pollution Control Ordinance, Specified Process Licences

In force

Air Pollution Control Ordinance (Cap. 311), ss. 2 and 13 and Schedule 1, item 7

Effective 1983-10-01 · Applies to both

The owner of premises must not use them, or permit them to be used, for the conduct of a specified process unless the owner holds a licence for that process. A specified process is a process specified in Schedule 1. Schedule 1 lists electricity works in which fossil fuel is burnt, wholly or as part of electricity generation, where the installed generation capacity of the works exceeds 5 MW.

An owner who contravenes the licence requirement is liable to a fine of 200,000 dollars and imprisonment for 6 months, plus a daily fine of 20,000 dollars while a continuing offence goes on. The Ordinance commenced on 1 October 1983.

Source: Full text of law

Every entry cites the instrument it describes. None of it is legal advice: verify a citation before relying on it. Full sourcing: read the methodology. The rest of the record: all jurisdictions.