Klimaneutrale Rechenzentren (Climate-Neutral Data Centres: Efficiency, Waste-Heat, Management-System and Reporting Duties)
In force
Energieeffizienzgesetz (EnEfG), §§ 11, 12, 13
Applies to both
Data centres that started operating before 1 July 2026 must be built and run to reach a power usage effectiveness (PUE) of 1.5 or lower from 1 July 2027 and 1.3 or lower from 1 July 2030, on a durable annual average.
A data centre starting operation on or after 1 July 2026 must reach a PUE of 1.2 or lower and a reused-energy share, under the DIN EN 50600-4-6 standard, of at least 10 percent, rising to at least 15 percent for a data centre starting from 1 July 2027 and at least 20 percent for one starting from 1 July 2028, each within two years of starting operation; the reused-energy share does not apply where the operator shows the share later became unattainable for reasons beyond its control, where an agreement with a nearby municipality or heat-network operator commits to building the network within ten years, or where a nearby heat-network operator fails within six months to accept the operator's offer to supply reused heat at cost.
Operators must also cover their data centres' electricity consumption 50 percent from renewable sources from 1 January 2024 and 100 percent from 1 January 2027, on a balance-sheet basis. Separately, operators of data centres must establish an energy or environmental management system by 1 July 2025, continuously measure the electrical power and energy demand of the facility's essential components, and take measures continuously improving its energy efficiency.
A data centre with at least 1 megawatt of non-redundant rated connected capacity, or at least 300 kilowatts if publicly owned or operated for a public body, must have that management system validated or certified from 1 January 2026, though a data centre whose reused energy supplies at least half of a heat network and whose average total final energy consumption over the preceding three calendar years is at most 7.5 gigawatt-hours is exempt from the management-system duty.
The same duties apply correspondingly to operators of information technology, with their own connected-capacity thresholds. Finally, a data centre operator must publish, and submit to the federal government by 31 March each year, information about the data centre for the preceding calendar year as specified in the Act's Annex 3.
Source: Full text of law
Netzanschluss (Grid Connection Obligation)
In force
Energiewirtschaftsgesetz (EnWG), § 17
Applies to both
Operators of energy-supply networks must connect end consumers, downstream networks, electric-vehicle charging points, generation and gas-storage installations, biogas processing plants, and electrical-energy storage installations to their network on technical and economic terms that are appropriate, non-discriminatory, transparent, and no less favourable than the terms the operator applies within its own group or to affiliated undertakings.
A network operator may refuse a connection only where it proves that granting it is operationally, economically or technically impossible or unreasonable, must give written reasons for a refusal, and, where capacity is the constraint and the applicant requests it, must also state the measures and associated costs that expanding the network would require.
Source: Full text of law