A data centre in Cyprus connecting to the electricity transmission or distribution network falls under the general licensing and connection-charging framework of the Electricity Market Law, regulated by the Cyprus Energy Regulatory Authority (ΡΑΕΚ).
No Cyprus-specific data-centre siting, environmental-review, or investment-incentive statute distinct from the general planning and building-permit regime was located in the primary sources checked within this visit's search budget; land-use, environmental-review, and construction-permitting coverage for Cyprus remains unresearched here.
01
Instruments on record
1 instrument on record, grouped by the family of approval each one governs.
Energy and grid
What authorizations govern grid connection and onsite generation?
Electricity Market Law, Article 98 (Transmission and Distribution Connection Charges)
In force
L. 130(I)/2021, art. 98
Applies to both
Cyprus's transmission system operator and distribution system operator must each prepare, for the energy regulator's approval, a report setting the basis for charges for use of and connection to the transmission or distribution system, including the capital cost of any additional new investment the connection requires, per Article 98(1) and (2) of the Electricity Market Law.
The Cyprus Energy Regulatory Authority may give binding regulatory directions on the charging basis for use of or connection to either network, per Article 98(3).
Source: Full text of law