Data-center law in Austria

National jurisdiction · as of 2026-10-12

Drafted with AI

Drafted with AI from the cited sources under the direction of UnGovr staff. UnGovr holds editorial responsibility for this page. How this site is made

Austria's Umweltverträglichkeitsprüfungsgesetz 2000 (UVP-G 2000) subjects a project to mandatory environmental impact assessment only if it falls within a closed list of project types in the Act's Annex 1; a data center is not one of the listed types, so building one triggers no UVP obligation regardless of its scale, energy draw, or water use. A large data center instead assembles its approvals across several established federal regimes.

Any commercial facility whose machinery, equipment or mode of operation could endanger life, health or property, or cause a nuisance to neighbours through odour, noise, smoke, dust or vibration, needs a commercial-facility permit (Betriebsanlagengenehmigung) under the Gewerbeordnung 1994 (GewO 1994), granted where the state of the art keeps the foreseeable hazards and nuisances within a tolerable level and, for air pollutants, within the Immissionsschutzgesetz-Luft's limits.

Grid connection runs through the Elektrizitätswirtschaftsgesetz (ElWG), which took over the federal connection duty from the former Elektrizitätswirtschafts- und -organisationsgesetz 2010 on 24 December 2025: a distribution network operator must conclude a private-law connection contract with any end customer, and may refuse only for a substantiated safety concern or a technical incompatibility of the system components.

Where the project draws groundwater or surface water for cooling or discharges water back to a watercourse, a water-use permit under the federal Wasserrechtsgesetz 1959 (WRG 1959) applies.

Building permitting itself is a matter for the Land in which the project sits, under that Land's own Bauordnung; Vienna has gone further than most Länder and, under 2026 amendments to its own energy law, requires a cost-benefit analysis and a permit before a data centre above 1 megawatt of nominal total energy input is built or substantially modernised there, and requires an existing data centre above that threshold to put its waste heat to use.

On energy efficiency, the Bundes-Energieeffizienzgesetz (EEffG) requires any large enterprise, or one that crosses the turnover or staffing thresholds the Act sets, to carry out a recurring energy audit or run a certified energy or environmental management system; a data-centre operator that qualifies is bound the same as any other large enterprise.

Separately, and naming data centres specifically, the EEffG requires the owner or operator of a data centre with at least 500 kilowatts of installed information-technology capacity to publish and keep current, from 15 May 2024 and every year after, a set of minimum disclosures on the facility's site, energy use, cooling, water use and renewable-energy share, transposing Article 12 and Annex VII of Directive (EU) 2023/1791; a data centre used solely for national defence or civil protection is exempt. No federal incentive regime targeted at computing infrastructure has been located.

01

Instruments on record

6 instruments on record, grouped by the family of approval each one governs.

Energy and grid

What authorizations govern grid connection and onsite generation?

Bundes-Energieeffizienzgesetz, Section 72a, Data Centre Reporting Duty

In force

EEffG Sec. 72a, BGBl. I Nr. 59/2023 as amended

Effective 2024-04-18 · Applies to both

Section 72a(1) obliges the owner and the operator of a data centre with at least 500 kilowatts of installed electrical capacity for information technology to publish, from 15 May 2024 and every year after by 15 May, and to keep current, the minimum information Section 72a(3) lists, except information covered by a confidentiality duty or a trade or business secret.

Section 72a(2) exempts a data centre used solely for national defence or for population protection, including civil and disaster protection.

Section 72a(3) requires publication of the data centre's name, owner, operator, commissioning date and municipality; its floor area, installed capacity, annual incoming and outgoing data traffic and the volume of data it stores and processes; its efficiency over the last full calendar year against key indicators including energy consumption, power usage, temperature setpoints, waste-heat use, water consumption and renewable-energy use; and any further information a delegated act under Article 33(3) of Directive (EU) 2023/1791 requires.

The term 'data centre' is defined at Section 37 Z 33 as a structure or group of structures used to house, network and run computer systems or servers and associated equipment for storing, processing or distributing data, and related activities, following Annex A point 2.6.3.1.16 of Regulation (EC) No 1099/2008 on energy statistics.

Source: Full text of law

Bundes-Energieeffizienzgesetz, Sections 41 and 42, Energy Audits and Management Systems for Large Enterprises

In force

EEffG Sec. 41-42, BGBl. I Nr. 59/2023 as amended

Effective 2023-06-15 · Applies to private

Section 41(1) obliges an enterprise established in Austria to carry out an energy audit or set up a recognised management system if it is a large enterprise, if it crosses the size thresholds the Act sets, or if it forms part of a corporate group whose combined figures cross those thresholds. Enterprises more than half owned by, or owning more than half of, another enterprise are aggregated for this test.

Section 42(1) lets the obligated enterprise satisfy the duty by an energy audit at least once every four years, carried out by a certified energy auditor, or by a certified energy-management or environmental-management system built on a recognised standard; Section 42(2) requires either route to meet the minimum requirements the Act's Annex 1 sets.

A data-centre operator that meets Section 41's thresholds is bound by this audit or management-system duty the same as any other large enterprise, regardless of its sector.

Source: Full text of law

Elektrizitätswirtschaftsgesetz, Section 95, General Connection Obligation of Distribution Network Operators

In force

ElWG Sec. 95, BGBl. I Nr. 91/2025

Effective 2025-12-24 · Applies to both

Section 95(1) obliges a distribution network operator to conclude a private-law connection contract with end customers, energy-storage operators, generators and other network operators; the contract is governed by the general network conditions set under Section 93.

Section 95(2) obliges the operator to connect a facility without delay at a suitable point, and the obligation holds even where feeding in or drawing power first becomes possible only once the operator optimises, reinforces or expands its network, which the operator must then do without delay.

Section 95(3) confines exceptions from the connection obligation to a substantiated safety concern or a technical incompatibility of the system components, and requires the operator to give the applicant a transparent, traceable reason for any refusal. Section 95 replaced the equivalent connection duty in the former Elektrizitätswirtschafts- und -organisationsgesetz 2010 (ElWOG 2010), which went out of force the same day.

Source: Full text of law

Wiener Energie- und Klimarechts-Umsetzungsgesetz 2020, Data Centre Cost-Benefit Analysis, Permit and Waste Heat Duties

In force

WERUG 2020 Sec. 7 to 10 and 22, LGBl. für Wien Nr. 28/2026

Effective 2026-07-17 · Applies to both

The Wiener Energie- und Klimarechts-Umsetzungsgesetz 2020 (WERUG 2020), as amended by the Wiener Energierechts-Änderungsgesetz 2026, contains a chapter implementing Article 26(6) to (12) of Directive (EU) 2023/1791. It defines a data centre by reference to point 2.6.3.1.16 of Annex A to Regulation (EC) No 1099/2008. Section 7(1) requires a cost-benefit analysis in accordance with Annex 1 before the construction and operation or substantial modernisation of the installations it lists.

Those installations include a data centre with a nominal total energy input of more than 1 MW. Section 8(1) makes the construction and operation of new installations of that kind, and their substantial modernisation, subject to a permit.

The permit is to be granted if the planned installation ensures efficient energy generation according to the state of the art and if the cost-benefit analysis starts from correct assumptions, matches the guiding principles of Annex 1, and is comprehensible and conclusive.

Section 9(2) lists among the cases needing no permit a data centre whose waste heat is or is to be used in a district heating network, or directly for space heating, domestic hot water preparation or other purposes in the building, group of buildings or facilities where it is located. Section 10(1) requires an existing data centre with a nominal total energy input of more than 1 MW to use its waste heat or other heat recovery applications.

A data centre that can show by a cost-benefit analysis under section 7 that heat recovery is technically or economically not feasible is exempt from that duty. On the operator's application, the authority must establish that there is no obligation to use waste heat where the conditions are met. The Magistrat der Stadt Wien is the competent authority for enforcing the chapter and for administrative penalty proceedings.

Section 22(1) punishes with a fine of up to 25,000 euro anyone who builds, operates or substantially modernises such an installation without the required permit, or who operates a data centre without using its waste heat or other heat recovery applications as section 10(1) requires. The amending Act was issued in the Landesgesetzblatt für Wien on 16 July 2026 as number 28 of 2026. Section 26(1) of WERUG 2020 provides that the changes made by the Act take effect on the day after its promulgation.

Source: Full text of law

Water and utilities

Who commits water and sewer service, and under what assessment?

Wasserrechtsgesetz 1959, Sections 9 and 10, Water-Use Permit Requirement

In force

WRG 1959 Sec. 9-10, BGBl. Nr. 215/1959 as amended

Applies to both

Section 9(1) requires a water-rights authority's permit for any use of a public watercourse beyond ordinary common use, and for building or altering a facility used for that purpose. Section 9(2) extends a permit requirement to a private watercourse where the use could affect a third party's rights or the water's flow, character, or level, or risk flooding or waterlogging another's land.

Section 10(1) lets a landowner draw groundwater for ordinary household and business needs without a permit where extraction is by hand-operated pumping or drawing equipment only or is proportionate to the owner's own land. Every other groundwater development or use, and the construction or alteration of a facility serving it, requires a water-rights permit. An artesian well always requires a permit.

A data center's cooling-water withdrawal from a river or aquifer, or its discharge of water back to a watercourse, falls within this permit requirement rather than under the UVP-G's environmental impact assessment, since the UVP-G's Annex 1 lists no data-center project category.

Source: Full text of law

Air and operations

What permits govern backup generators and ongoing emissions?

Gewerbeordnung 1994, Sections 74 and 77, Commercial Facility Permit (Betriebsanlagengenehmigung)

In force

GewO 1994 Sec. 74, 77, BGBl. Nr. 194/1994 as amended

Applies to private

Section 74(1) defines a commercial facility (gewerbliche Betriebsanlage) as any spatially fixed installation intended to serve a commercial activity on more than a temporary basis.

Section 74(2) requires an authority's permit before such a facility may be erected or operated if, because of its machinery, equipment, mode of operation or other characteristics, it could endanger life, health or property, cause a nuisance to neighbours through odour, noise, smoke, dust or vibration, impair a nearby public-interest facility, materially disrupt traffic, or adversely affect a watercourse unless a water-rights permit already covers that effect.

Section 77(1) requires the authority to grant the permit where, given the state of the art, the foreseeable hazards can be avoided and the nuisances kept within a tolerable level, attaching conditions where needed. Section 77(3) requires the authority to limit air-pollutant emissions to the state of the art and to apply the Immissionsschutzgesetz-Luft's ordinances, tightening the test in an area that already exceeds designated air-quality limit values.

The statute names no data centre; a data centre operated as a commercial activity is a commercial facility within this definition, and erecting or operating one needs this permit where the permit criteria are met.

Source: Full text of law

Every entry cites the instrument it describes. None of it is legal advice: verify a citation before relying on it. Full sourcing: read the methodology. The rest of the record: all jurisdictions.